Equipment Cost Codes: How to Track Labor and Equipment on the Same Job
Learn how to track labor and equipment under the same construction cost codes, allocate machine hours, and prevent duplicate wages, fuel, and rental costs.
Quick Answer
Use the same job and phase cost code for labor and equipment, but record them under separate Labor and Equipment cost types. For example, EXC-200 Excavation can carry one Labor line for operator wages and a separate Equipment line for excavator hours. This is the basic equipment cost type distinction. Keep operator wages out of the machine rate if they are already charged as labor, and decide whether fuel, maintenance, and rental costs will be allocated through internal equipment rates or charged directly. Reconcile equipment usage, rate calculations, invoices, and accounting entries before reporting job costs to prevent duplicate charges.
When an excavator and its operator work on the same excavation phase, their costs should appear under that phase without being combined into one expense category.
The excavation cost code identifies the work. Separate Labor and Equipment cost types preserve the operator’s wages and machine charges, allowing the controller to review each amount and identify overlapping expenses.
For the broader setup, see Workyard’s guides to construction cost codes and construction job costing.
What equipment cost codes should look like on a construction job
Construction equipment cost codes should identify the work performed, with Labor and Equipment separated by cost type under the same job and phase code.
The structure has three layers:
- Job: The contract or job receiving the cost.
- Phase or cost code: The activity being performed, such as excavation, grading, trenching, or backfill.
- Cost type: The resource creating the cost, such as Labor, Equipment, Material, or Subcontract.
Sage Construction Management recommends using cost codes to identify the work being performed while tracking labor, equipment, materials, and other expenses by resource type. Procore also identifies Labor and Equipment as separate cost types that can be paired with job cost codes.
For example, a sitework contractor could use EXC-200 Excavation as the shared phase code, with separate cost entries for:
- EXC-200 | Labor: Operator wages and applicable labor burden.
- EXC-200 | Equipment: Excavator and skid steer usage charges.
The excavation report can then show the total cost of the phase alongside its separate labor and equipment amounts.
Some accounting systems use resource classifications or combined codes instead of dedicated cost-type fields. The accounting system determines how these records are structured. Configure the excavation report, where supported, so the controller can review labor and equipment separately under EXC-200.
Example: labor and equipment on an excavation job
Consider a sitework contractor excavating a utility trench at Utility Site A. An operator works an eight-hour shift under EXC-200 Excavation, using an excavator for six hours before switching to a skid steer for the final two hours.
The contractor records the operator’s full shift under Labor and assigns the machine usage to Equipment.
| Job | Phase/cost code | Cost type | Source record | Quantity | Rate | Extended cost |
| Utility Site A | EXC-200 Excavation | Labor | Operator timecard | 8 hrs | $42/hr | $336 |
| Utility Site A | EXC-200 Excavation | Equipment | Excavator usage | 6 hrs | $95/hr | $570 |
| Utility Site A | EXC-200 Excavation | Equipment | Skid steer usage | 2 hrs | $48/hr | $96 |
| Total | $1,002 |
Illustrative example only. The $42 labor rate includes assumed labor burden. Equipment rates exclude operator wages and are applied to chargeable equipment usage. The $1,002 subtotal excludes materials, subcontractors, and other phase expenses.
The excavation phase has $336 in labor costs and $666 in equipment costs, producing a combined subtotal of $1,002. Both cost types roll up under EXC-200 without losing the underlying detail.
Keeping the records separate also accounts for changes during the shift. The operator worked eight hours, but the excavator only received six hours of usage. Charging the excavator for the entire shift would overstate its usage and could incorrectly allocate costs between machines.
The equipment rates must also reflect the contractor’s costing policy. Since operator wages are already included in Labor, the $95 excavator rate and $48 skid steer rate exclude those wages.
For more information about calculating machine rates, see Workyard’s guide to equipment hourly cost rates.
Three ways contractors accidentally count the same equipment cost twice
A job can show inflated equipment costs even when every timecard and equipment log is accurate. Problems arise when expenses already included in an internal equipment rate are also charged directly to the job.
The following examples show where those overlaps occur and how contractors can correct them.

1. Operator wages are included in both Labor and the equipment rate
Suppose a contractor uses a $95 hourly excavator rate that already includes the operator’s wages. The same operator also submits an eight-hour timecard coded to EXC-200 Labor.
If accounting applies both charges without adjusting for the overlapping wages, part of the operator’s labor cost appears twice.
For equipment operated by company workers, contractors commonly calculate labor and machine costs separately:
Labor cost = operator hours × burdened labor rate
Equipment cost = chargeable equipment hours × equipment rate excluding operator labor
This approach allows the excavation report to retain separate labor and equipment costs. The controller can review how much was spent on the crew and how much was allocated to the machine.
Composite equipment rates may include an operator, particularly for contracted or owner-operated equipment. Where those rates are used, accounting should account for the included wages when calculating the equipment charge so the job does not receive a duplicate labor allocation.
2. Fuel or maintenance is charged directly and included in the hourly rate
Internal equipment rates may recover depreciation, repairs, maintenance, fuel, lubrication, insurance, and other ownership or operating expenses.
Caltrans equipment rental rate guidance, for example, describes several of these components. Its rates apply in a government contracting context and should not be treated as mandatory internal rates for private contractors.
Suppose the excavator’s $95 hourly rate includes an allowance for fuel. If accounting also charges the actual fuel purchase directly to EXC-200, the job could receive overlapping fuel costs.
Contractors generally need to establish how these costs will reach the job:
- Through the equipment rate: Include the defined fuel or maintenance allowance in the hourly rate and reconcile any separate charges against that allocation.
- Through direct job charges: Exclude the relevant expense from the equipment rate and assign the actual cost to the appropriate job when it can be traced reliably.
Both methods require the actual expense to be recorded in accounting. The job-cost allocation depends on whether the equipment rate already includes it. If fuel is recovered through the rate, any separate fuel charge against the job needs to be reconciled so the same expense is not recovered twice.
The same treatment applies to maintenance. A repair invoice may still appear in the company’s accounting records even when an internal equipment rate recovers maintenance costs across jobs.
3. A rental invoice and an internal equipment charge hit the same machine
Rental costs can be duplicated when the company charges a vendor invoice directly to a job and also applies an internal rate intended to recover that invoice.
Suppose a contractor rents a backhoe for $3,000. Accounting posts the full rental invoice to the job, while the field team records 30 hours of equipment usage. An internal allocation of $100 per hour adds another $3,000.
If both charges remain in the job total without an offset, the report shows $6,000 for an underlying rental expense of $3,000.
Contractors may instead record the rental invoice in an expense or clearing account and use internal charges to distribute that cost across several jobs. In that setup, accounting needs corresponding offsets so the allocations do not duplicate the original expense.
Sage’s equipment job-costing guidance describes tracking rented equipment through supplier bills and equipment-related job-cost records.
Before assigning rental costs, the controller should determine whether the invoice will be charged directly to one job or distributed through an internal allocation method. Where multiple jobs share the rental, the allocation records should reconcile to the original expense and any applicable adjustments.
How equipment hours stay with the correct job and cost code
Equipment cost allocation depends on recording which machine was used, where it worked, and how many hours qualify for a charge. Those records should be maintained separately from the worker’s labor time.
The excavation example illustrates how assignments can change during a shift without changing the employee’s total hours.
One worker changes machines
The operator’s shift at Utility Site A is recorded as follows:
| Time | Labor assignment | Equipment assignment |
| 7:00 a.m. to 1:00 p.m. | EXC-200 Excavation | Excavator, 6 hours |
| 1:00 p.m. to 3:00 p.m. | EXC-200 Excavation | Skid steer, 2 hours |
In this simplified example, the operator has eight chargeable labor hours against EXC-200, with two separate equipment-use records supporting machine charges. It assumes no unpaid break within the shift. In a real shift, deduct applicable breaks or nonchargeable time according to the contractor’s timekeeping and costing policy.
A machine switch does not change the worker’s labor allocation if the worker remains on the same excavation code. Record the excavator and skid steer as separate equipment-use segments in the contractor’s equipment log. This is an example of an accounting workflow, not an automated Workyard equipment-hours feature. To choose how the underlying usage is captured, compare equipment time tracking, GPS, and telematics.
One machine changes operators
Suppose the excavator remains on EXC-200 throughout the day, but a second operator takes over after lunch.
The equipment record should identify the machine and the period assigned to the excavation phase. The contractor can also capture operator details when needed for review or billing.
Accounting should calculate the equipment charge using the applicable machine usage rather than adding together both operators’ full labor shifts.
One machine moves to another job or phase
An excavator may begin the day on excavation work and move to backfill later.
For example:
- EXC-200 Excavation: 4 chargeable equipment hours
- BF-400 Backfill: 3 chargeable equipment hours
Each phase receives the equipment cost associated with its recorded usage. The machine’s total daily charge can then be reconciled against the individual phase allocations.
This keeps the office from assigning an entire day’s machine-use charge to the first or last code used by the crew.
Equipment-use hours are not the same as engine runtime
Engine-hour meters and telematics records can help verify machine activity, but they do not necessarily identify the job or cost code that should receive the expense.
A machine may accumulate engine hours while idling, repositioning, or waiting for another crew. The contractor’s policy determines whether those periods are chargeable and whether they receive the full operating rate or another rate.
This distinction also affects construction equipment utilization. A machine can generate ownership expenses even when it is not performing productive work, so utilization records and chargeable job hours may support different calculations.
For a detailed discussion of collecting machine-use records in the field, see How to Track Equipment Hours on Construction Jobs.
Turn machine hours into equipment job costs
To allocate equipment cost to jobs, record chargeable machine hours against the correct job and phase, then multiply those hours by the applicable rate.
Equipment job cost = chargeable equipment hours × applicable equipment rate
In the excavation example, six chargeable excavator hours at $95 per hour produce a $570 equipment allocation to EXC-200.
Accurate equipment cost allocation depends on matching those hours to a documented internal rate. For owned machines, that rate may recover ownership and operating expenses. Rented equipment may instead be allocated using rental invoices or another documented method.
The internal equipment rate measures the cost assigned to the job. A customer billing rate may be different because it follows the contract’s pricing, markup, and equipment billing terms.
The contractor should establish which rate components apply before using them in a job-cost report. If an owned excavator’s internal rate includes depreciation, maintenance, and fuel, the accounting process must reconcile direct job charges for those expenses against the machine allocation.
Federal Highway Administration contract administration guidance discusses the use of actual cost records and established equipment-rate schedules in federal highway contracting. Those practices can help inform rate calculations, although the applicable contract and company policy determine how a contractor should treat its own equipment costs.
For the broader process of assigning owned and rented machine expenses to jobs, see Equipment Job Costing: How to Track the True Cost of Construction Equipment.
Workyard’s equipment hourly cost rate guide covers the rate calculation in more detail.
What accounting should receive
Accounting needs enough information to trace each equipment charge to its source and confirm that the correct job received the cost.
For Utility Site A, a job-cost allocation report might contain the following records:
| Job | Cost code | Cost type | Quantity | Rate | Amount |
| Utility Site A | EXC-200 | Labor | 8 hrs | $42 | $336 |
| Utility Site A | EXC-200 | Equipment | 6 hrs | $95 | $570 |
| Utility Site A | EXC-200 | Equipment | 2 hrs | $48 | $96 |
Illustrative job-cost allocation records, not a Workyard accounting export. Rates and amounts match the excavation example above.
The supporting records should preserve the job, cost code, cost type, employee or equipment ID, transaction date, chargeable hours or quantity, applied rate, extended amount, source reference, and any corrections. These details may be distributed across timecards, equipment logs, rate schedules, and accounting records rather than appearing in every export.
For example, if two excavator hours were assigned to EXC-200 instead of BF-400, correct the equipment allocation and preserve the original record or adjustment history. The operator’s labor timecard should remain unchanged if the recorded labor hours and code are accurate.
Accounting systems may organize the information differently. Some use dedicated cost types, while others rely on resource classifications or mapped accounts.
Contractors using QuickBooks can refer to Workyard’s guide to construction cost codes in QuickBooks for examples of organizing job-cost information. The available coding structure depends on the QuickBooks product and configuration.
Before closing the reporting period, the controller should verify that each equipment charge has a supporting record and that the rate applied matches company policy. Direct expenses, rental invoices, and internal allocations should be reconciled before the job total is finalized.
These records can support construction cost tracking by keeping labor and equipment expenses identifiable when reviewing job budgets and actual costs.
The management job-cost report may display detailed machine usage and internal allocations, while the accounting system uses summarized journal entries or a different posting structure. The supporting records need to remain available so accounting can trace amounts and resolve discrepancies without relying on the summary report alone.
How Workyard fits into the workflow today
Workyard helps contractors track labor hours against the correct jobs and cost codes. Crews can assign timecards to specific activities, while GPS tracking provides location information to help verify where workers clock in and out. Workyard uses labor records and configured cost rates to support job-cost reporting.
Accurate cost-code assignments also need to carry through to payroll. See How to Stop Hours Arriving at Payroll Without Their Construction Cost Codes for guidance on preventing missing codes and reducing office corrections.
For equipment documentation, Workyard offers Smart Forms as a separate add-on. Crews can submit equipment usage logs, inspections, and other field records. Smart Forms has calculation fields for quantity multiplied by unit cost, including equipment and material estimates. These form calculations do not establish native machine-hour costing, add equipment lines to Workyard’s labor job-cost reports, or post accounting entries.
Workyard’s currently available job-cost reporting focuses on labor costs. Native equipment-hours costing and combined Labor and Equipment job-cost reporting under the same cost codes have not launched. The equipment entries shown here are illustrative records maintained through the contractor’s existing equipment-costing process. Contractors should use their established equipment-costing process to calculate machine charges and reconcile them with labor and other job expenses.

As a Construction Operations Platform, Workyard helps contractors capture reliable field data and automate the work around the job. Accounting remains responsible for financial posting and reconciliation.
Equipment cost-code checklist
Before using equipment rates across jobs, confirm that the coding structure and allocation method are documented.
- Use cost codes for the work being performed. Keep Labor and Equipment beneath the same phase where the accounting structure supports it.
- Preserve separate cost types. Labor and equipment charges should remain identifiable in the job-cost report.
- Document internal equipment rates. Specify whether the rate includes operator wages, fuel, maintenance, depreciation, and other ownership or operating expenses.
- Check operator labor treatment. Avoid allocating the same wages through a labor timecard and an overlapping composite machine rate.
- Reconcile direct expenses. Review fuel, maintenance, and rental charges against the costs already recovered through equipment rates.
- Record machine changes accurately. Capture equipment usage by machine, job, and phase without altering otherwise accurate labor records.
- Preserve corrections. Keep supporting information when equipment hours or cost-code assignments are adjusted.
- Review allocations before reporting. Confirm that equipment charges, invoices, and applicable offset entries reconcile.
For the excavation example, the controller should be able to trace the $336 labor charge to the operator’s timecard and the $666 equipment charge to the two machine-use records and their respective rates.
Before reporting the job total
Labor and equipment can share a job and phase cost code while remaining separate cost types. This lets contractors review total phase costs without losing the detail behind operator wages and machine charges.
Before reporting the job total, verify that equipment rates, direct expenses, rental invoices, and any offset entries have been reconciled. That check helps prevent duplicate costs from overstating job expenses and understating margins.
References
- 1
Sage Construction Management. Master Cost Codes FAQ. https://help.sagecm.intacct.com/Content/GettingStarted/ImplementationPlan_Financials_Opt_MasterCostCodes_FAQ.htm
- 2
Procore. What Are Procore’s Default Cost Types? https://support.procore.com/faq/what-are-procores-default-cost-types
- 3
California Department of Transportation. Equipment Rental Rates FAQ. https://dot.ca.gov/programs/construction/equipment-rental-rates-and-labor-surcharge/equipment-rental-rates-faq
- 4
Sage Construction Management. Equipment Job Costing Overview. https://help.sagecm.intacct.com/Content/Modules/Equipment/EquipmentJobCosting/EquipmentJobCostingOverview.htm
- 5
Federal Highway Administration. Contract Administration: Equipment Rates. https://www.fhwa.dot.gov/construction/contracts/0635asup.cfm
Yes. Labor and equipment can share a job and phase cost code while being recorded under separate cost types.
For example, EXC-200 Excavation can contain an operator’s wages under Labor and excavator usage charges under Equipment. The job-cost report can then show the total excavation cost and the separate amounts contributing to it.
The exact coding arrangement depends on the contractor’s accounting system.
A cost code identifies the activity receiving the expense, such as excavation or backfill. A cost type identifies the resource creating the expense, such as Labor or Equipment.
Some accounting systems store these classifications separately, while others combine them into longer account or budget codes.
Operator wages can be included in a documented composite equipment rate, but accounting must prevent the same wages from being charged again through a separate labor allocation.
For company-operated equipment, contractors can keep operator wages under Labor and apply a machine rate that excludes those wages.
Fuel can be allocated through an internal equipment rate or charged directly to a job, depending on the contractor’s policy.
When the rate already includes fuel, any separate fuel expense allocated to the same job should be reconciled to prevent duplicate recovery. The actual purchase still needs to be recorded in the appropriate accounting account.
Decide whether the rental invoice will be charged directly to the job or distributed using an internal equipment allocation method.
If accounting records the invoice and uses internal charges to distribute the cost, corresponding offsets or clearing entries should prevent both amounts from increasing the job total for the same expense.
The job-cost ledger should show separate Labor and Equipment amounts under the appropriate job and phase code.
For EXC-200 Excavation, the illustrative records show $336 in Labor and $666 in Equipment, giving a combined subtotal of $1,002.
Accounting should be able to trace those charges to the operator’s timecard, machine-use records, applied rates, and any supporting invoices or adjustments. The exact ledger layout depends on the accounting system.