Blower Door Test Report

Records a blower door test from baseline conditions and sealing through single-point and multi-point readings, with photos at each step.

WordExcel
  • No email
  • No sign-up
  • Edit it, add your logo

19 checks · 9 sections · Updated Nov 2026

See every check

The template

The full Blower Door Test Report

Print it for the clipboard, or put it on your crew’s phones. Same 19 checks either way.

Your logo

Blower Door Test Report

Prove envelope airtightness & improve compliance with this Blower Door Test Report. The template is inspired by ASTM E779, ISO 9972, and RESNET/ICC 380 steps: it records fan data, pressure readings, ACH50 targets from the 2021 IECC, photos of leaks, and corrective seals.

Job
Date
Address
Builder / Contractor
Test Date
Climate Zone
Tester Name & Certification #
Conditioned Floor Area (ft²)
Building Volume (ft³)
Fan Serial #
Fan Calibration Date
Target ACH₅₀

1 · Baseline Conditions

Inspection

InspectionValueNotes
Indoor Temp (°F/°C)
Outdoor Temp (°F/°C)
Barometric Pressure (inHg)
Wind Speed / Dir
Indoor RH (%)

2 · Setup & Sealing

2 · Setup & SealingYNN/A
2.1Exterior doors and windows closed (not sealed beyond normal weatherstripping)
2.2Fireplace doors and flue damper closed (not sealed)
2.3HVAC system off; supply and return registers fully open
2.4Exhaust, intake and makeup-air dampers closed (not sealed); continuous ventilation openings sealed
2.5Interior doors open; plumbing traps filled
2.6Combustion appliances off or set to pilot
2.7Fan mounted securely in exterior door/frame
2.8Manometer zeroed and hoses connected
2.9Other (describe)

Photos - Setup & Sealing · photo refs

3 · Single-Point Test

3 · Single-Point TestYN
3.1Pressure (Pa)
3.2Flow (CFM₅₀)
3.3CFM₅₀ / ft² (cfm50 per ft²)
3.4Other (describe)

Photos - Single Point Test · photo refs

4 · Multi-Point Curve

Pressure (Pa)

Pressure (Pa)Building Pressure (Pa)Fan Pressure (Pa)Measured Flow (CFM)Note
15
20
25
35
50
60
Other (describe)

Photos - Multi-Point Curve · photo refs

5 · Leak Hunt

5 · Leak HuntYN
5.1Smoke Pencil
5.2Infrared Camera (IR)
5.3Other (describe)

Photos - Leak Hunt · photo refs

6 · ACH₅₀ Calculation

Building Volume (ft³)
Measured CFM₅₀
Calculated ACH₅₀
Meets Target?YesNo

7 · Fixes

Log

IssueFix AppliedNotes

Additional Photos & Documentation · photo refs

8 · Verification Test

8 · Verification TestYN
8.1Pressure (Pa)
8.2Flow (CFM₅₀)
8.3Calculated ACH₅₀

Photos & Supporting Documentation - Verification test · photo refs

9 · Sign-Off

Tester

Name
Signature
Inspection Date

QA Reviewer (if required)

Name
Signature
Date

Owner / AHJ Rep (if required)

Name
Signature
Date

References & Standards

  • 2021 IECC § R402.4.1.2 – Air-leakage testing requirement
  • ASTM E779 – Determining air-leakage rate by fan pressurization
  • ISO 9972 – Air-permeability measurement of building envelopes
  • ANSI/RESNET/ICC 380 – Standard for testing airtightness of buildings

Your AHJ and the code edition it has adopted govern. This checklist supports your inspection; it doesn’t replace the one your jurisdiction requires.

Free download

Blower Door Test Report template: PDF, Word and Excel

Print the form as it is, or download a template you can edit. Every format is free, with no email and no sign-up.

How to use it

How to run the Blower Door Test Report

  1. 01

    Check it at the hold point

    Run it before the next trade covers the work, against the plans and the spec.

  2. 02

    Work the sections in order

    Go through the 9 sections in order. Measure where it asks for a number; don’t eyeball it.

  3. 03

    Log every miss with a photo

    Write down what doesn’t meet spec, who fixes it and by when, and attach a photo.

  4. 04

    Sign off when it’s right

    Re-check the fixes, then sign. The signed sheet is your proof the work met spec when it was built.

Why we built this

Rework is the most expensive work you’ll do

A miss caught at the hold point is a quick fix. Caught after the next trade has covered it, it’s a tear-out, a delay and a margin gone.

  • Built for the field. Every check is written the way crews talk, with room for notes, photos and a signature.
  • Free, with no catch. No email, no account. Print it and hand it out.
  • On paper or on the phone. The same form runs on the Workyard app, filed to the job when it’s sent.

3,000+contractors run their crews on Workyard

Meet Workyard

Who we are

Workyard is the construction operations platform for specialty contractors and self-performing general contractors determined to grow without sacrificing job control or margins.

Forms like this one are what our customers’ crews fill in on Workyard every day, on the same app they clock in with.

workers on Workyard every day
100,000+
free templates, none of them gated
182

Forms & Workflows

Get every form back from every crew, every day

  • It shows up on its own. Attach it to a task, a job or clock-out, and it’s on the crew’s phone when it’s due.
  • It can’t be skipped. Make it required and the day can’t close until it’s in.
  • You see it the same day. Filed, flagged or missing, every job on one board, before anyone has to call.

$123,000cut from insurance costs at TR3 Group

More quality control templates

Free templates for the rest of the job

Browse all templates

Questions

Blower Door Test Report FAQs

When should a blower door test be performed?

Perform the test on every new build, major renovation, or weatherization project, and again after substantial air-sealing work. Repeat testing documents improvement, assures lenders and rebate programs the work achieved its goal, and keeps you compliant with energy-code commissioning requirements.

Who can sign the Blower Door Test Report?

A certified HERS rater, BPI Building Analyst, or other authority recognized by the jurisdiction should sign. Their credential number, calibration date, and digital signature confirm the fan and gauges met accuracy rules and that the data conforms to ASTM E779 and RESNET/ICC 380.

Can the test be done in windy conditions?

Standards allow testing when average wind speed is below roughly 10 mph; higher gusts distort pressure data. Monitor wind, record it, and if turbulence exceeds limits pause, perform interior leakage checks, or return later. Documenting conditions prevents officials questioning the reliability of the results.

What if the building fails the target ACH50?

If leakage exceeds the limit, identify priority gaps with smoke or infrared, seal them, then retest. Record each fix and new reading. Most jurisdictions accept iterative testing, provided the final signed report shows compliance before the certificate of occupancy is issued.

Do I need a Workyard account to use it?

No. Print the paper form, save it as a PDF, or download the Word or Excel file, free, with no email and no sign-up. You only need an account to put the digital form on your crew’s phones.

Can I edit the template?

Yes. Download the Word or Excel version to add your logo, add checks from your project spec or remove sections you don’t need. They open in Google Docs and Google Sheets too.

How do I get my crew to fill it in on their phones?

Add the digital form to Workyard and attach it to the job or the task it belongs to. It shows up in the app your crew already clocks in with, and every form comes back signed, with its photos, filed to the job.

Trigger the form at the right moment

A job's Forms tab in Workyard: each form, the clock-in or clock-out that triggers it, and how many have been submitted
A van check filled in on the Workyard app: the damage photo, a description and the tech's signature, ready to submit

Book a demo with a Workyard specialist

Your local Workyard specialist

Works with 50 contractors across the US

Your details

30 min · Video call