Daily report templates give the person running a crew one form to record a working day on a job: who was there and for how long, what got done, what equipment ran, what was delivered, the weather, delays, safety notes and photos. Superintendents, foremen and subcontractor leads fill them in at the end of each shift, and the office, the owner and the GC read them to track progress and settle questions later.

What is a daily report in construction?

A daily report in construction is the dated, signed account of one day on one job. It records facts, not opinions: headcount and hours by trade, work completed by area, equipment hours, materials received, inspections, incidents, weather and anything that held the work up. Taken together, a job's daily reports are its diary. They back up pay applications and change orders, explain schedule slips, and answer the question "what actually happened on the 14th?" long after anyone remembers.

Daily report templates: which one to use

The construction daily report forms in this category each fit a different role or kind of job.

TemplateBest for
Daily Construction ReportThe standard end-of-day report: weather, crews, equipment, materials, progress, inspections and safety
General Contractor Daily LogThe GC's record of the whole site, including subs, visitors, inspections and delays
Subcontractor Daily ReportA sub's foreman reporting labor, equipment, materials and safety to the GC
Daily Safety and Productivity ReportWork, crew hours and equipment with safety observations and near misses
Heavy/Civil Construction Daily ReportEarthwork, paving and utility jobs with heavy equipment and haul counts
Restoration/Damage Repair Daily ReportWater and fire jobs: demo, moisture and atmospheric readings, drying equipment
Daily Jobsite Housekeeping ChecklistA daily check of floors, stairs, storage, waste and exits with corrective actions

Daily report vs daily log

People use the terms loosely, and our daily log templates and daily reports overlap. In practice, a daily log is the GC's running site record, kept for the job file, while a daily report is often the version sent to someone: the owner, the GC from a sub, or the office. If your contract names one, use the format it asks for. Most GCs keep the general contractor daily log and collect a subcontractor daily report from each trade.

How to make a daily progress report that holds up

A daily progress report is only useful if someone who wasn't on site can read it and know what happened. Write quantities and locations, name causes, and attach proof. Compare two entries for the same day:

  • Weak: "Framing ongoing. Some delays. Concrete late."
  • Strong: "Framing crew of 6, level 2 walls grid A to D complete. Concrete pump arrived 10:40, scheduled 8:30; 2 hours lost on the slab pour, superintendent notified at 8:45. Photo of the empty pump pad at 9:00 attached."

The second one settles a backcharge argument; the first starts one. Use the same names for areas, trades and materials every day so entries line up when you search back. Report every day the job is active, including days lost to weather.

Daily reports on crews' phones, or free to download

In Workyard, every template here is a digital form your foreman fills in on a phone at clock-in or before leaving the job, with photos and a signature on screen. Answers you flag, like an incident or a delay, go to the person you name, and every report is filed to the job in the office, ready to export as PDF or CSV. See daily reporting in Workyard. Each template is also free to download as a PDF, Word or Excel file, with no sign-up. For a field-wide start, try the daily construction report.