Hot Work Authorization: Is this welding being done in a designated safe welding area?
YesNo
Has a Hot Work Permit been issued/authorized for this job?
YesNo
Permit #/ID
Enter text
Job Date & Time
Select a date
Exact Location of Work
Enter text
Personnel Qualifications & Briefing
Check qualifications and hazard communication per OSHA 1926 Subpart J (1910.252 in general industry).
Welder Training VerifiedYesNo
Briefing CompletedYesNo
Reference Materials ReviewedYesNo
Comments
Enter text
Personal Protective Equipment (PPE)
Verify required PPE is used per OSHA 1926 Subpart E (1910 Subpart I in general industry) and ANSI Z49.1.
Welding Helmet/ShieldYesNo
Safety Glasses/GogglesYesNo
Welding GlovesYesNo
FR Protective ClothingYesNo
Proper Clothing FitYesNo
BootsYesNo
Hearing ProtectionYesNo
RespiratorYesNo
Comments
Enter text
Work Area & Fire Safety
Inspect area for fire hazards per OSHA 1926.352 (1910.252(a) in general industry) and NFPA 51B.
Combustibles Cleared Within 35 ft (or Shielded)YesNo
Floor CleanYesNo
Combustible Flooring ProtectedYesNo
Openings CoveredYesNo
Adjacent Areas SafeYesNo
No Flammable AtmosphereYesNo
Fire Sprinklers/Alarms ActiveYesNo
Fire Extinguisher ReadyYesNo
Correct Fire ExtinguisherYesNo
No Unauthorized AreaYesNo
Comments
Enter text
Welding Equipment Inspection
Verify safe setup and condition per OSHA 1926.350 and 1926.351 (1910.253 and 1910.254 in general industry).
Machine ConditionYesNo
Cables & Leads IntactYesNo
Frame GroundedYesNo
Electrode Holder SafeYesNo
Cylinders SecuredYesNo
No Leaks in HosesYesNo
Flashback ArrestorsYesNo
Screens in PlaceYesNo
Wet Conditions AddressedYesNo
Comments
Enter text
Ventilation and Fume Control
Ensure adequate ventilation per OSHA 1926.353 and 1926.354 (1910.252(c) in general industry) and 1910.134.
Adequate VentilationYesNo
Confined Space TestedYesNo
Ventilation ContinuousYesNo
Fume Source ControlYesNo
Respirator UsedYesNo
Coatings RemovedYesNo
Plume AvoidanceYesNo
Comments
Enter text
Fire Watch & Emergency Readiness
Verify fire watch and response readiness per OSHA 1926.352(e) (1910.252(a)(2)(iii) in general industry).
Fire Watch RequiredYesNo
Fire Watch AssignedYesNo
Fire Extinguisher ReadyYesNo
Understands DutiesYesNo
Knows Alarm ProcedureYesNo
Fire Watch ≥ 30 Min After Work (1 Hr per NFPA 51B)YesNo
Extended MonitoringYesNo
Adjacent Areas MonitoredYesNo
Comments
Enter text
Final Sign-off
All pre-work welding safety checklist items satisfactory?
YesNo
Pre-Work Safety Inspection Completed By
Enter text
Signature
Sign here
Date & Time
Select a date
Photo
Post-Work Completion Acknowledgment (Optional): The work area was monitored for the required cool-down period after welding, and no signs of fire or hazards remain.
YesNo
Final check performed by
Enter text
at (time)
Enter text
Signature
Sign here
Submit
Scroll through the form
The template
The full Welding Safety Checklist
Print it for the clipboard, or put it on your crew’s phones. Same 45 checks either way.
Your logo
Welding Safety Checklist
The Welding Safety Checklist supports safe welding practices by confirming PPE use, ventilation, equipment condition, and site readiness. Help reduce fire hazards, burns, and exposure risks with routine safety checks.
Job
Date
Welder’s Name
Supervisor or Permit Authorizing Individual
Description of Work
Hot Work Authorization: Is this welding being done in a designated safe welding area?YesNo
Has a Hot Work Permit been issued/authorized for this job?YesNo
Permit #/ID
Job Date & Time
Exact Location of Work
1 · Personnel Qualifications & Briefing
1 · Personnel Qualifications & Briefing
Y
N
1.1
Welder Training Verified
1.2
Briefing Completed
1.3
Reference Materials Reviewed
Comments
2 · Personal Protective Equipment (PPE)
2 · Personal Protective Equipment (PPE)
Y
N
2.1
Welding Helmet/Shield
2.2
Safety Glasses/Goggles
2.3
Welding Gloves
2.4
FR Protective Clothing
2.5
Proper Clothing Fit
2.6
Boots
2.7
Hearing Protection
2.8
Respirator
Comments
3 · Work Area & Fire Safety
3 · Work Area & Fire Safety
Y
N
3.1
Combustibles Cleared Within 35 ft (or Shielded)
3.2
Floor Clean
3.3
Combustible Flooring Protected
3.4
Openings Covered
3.5
Adjacent Areas Safe
3.6
No Flammable Atmosphere
3.7
Fire Sprinklers/Alarms Active
3.8
Fire Extinguisher Ready
3.9
Correct Fire Extinguisher
3.10
No Unauthorized Area
Comments
4 · Welding Equipment Inspection
4 · Welding Equipment Inspection
Y
N
4.1
Machine Condition
4.2
Cables & Leads Intact
4.3
Frame Grounded
4.4
Electrode Holder Safe
4.5
Cylinders Secured
4.6
No Leaks in Hoses
4.7
Flashback Arrestors
4.8
Screens in Place
4.9
Wet Conditions Addressed
Comments
5 · Ventilation and Fume Control
5 · Ventilation and Fume Control
Y
N
5.1
Adequate Ventilation
5.2
Confined Space Tested
5.3
Ventilation Continuous
5.4
Fume Source Control
5.5
Respirator Used
5.6
Coatings Removed
5.7
Plume Avoidance
Comments
6 · Fire Watch & Emergency Readiness
6 · Fire Watch & Emergency Readiness
Y
N
6.1
Fire Watch Required
6.2
Fire Watch Assigned
6.3
Fire Extinguisher Ready
6.4
Understands Duties
6.5
Knows Alarm Procedure
6.6
Fire Watch ≥ 30 Min After Work (1 Hr per NFPA 51B)
6.7
Extended Monitoring
6.8
Adjacent Areas Monitored
Comments
7 · Final Sign-off
All pre-work welding safety checklist items satisfactory?YesNo
Pre-Work Safety Inspection Completed By
Name
Signature
Date
Date & Time
Photo · photo refs
Post-Work Completion Acknowledgment (Optional): The work area was monitored for the required cool-down period after welding, and no signs of fire or hazards remain.YesNo
Final check performed by
at (time)
Name
Signature
Date
Welding Safety Checklist on a phone
Welding Safety Checklist
Job *
26-104 Riverside DuplexesSelect a job
Oct 14, 8:12 AM26-104 Riverside Duplexes
Personnel Qualifications & Briefing
Check qualifications and hazard communication per OSHA 1926 Subpart J (1910.252 in general industry).
Welder Training VerifiedYesNo
Briefing CompletedYesNo
Reference Materials ReviewedYesNo
Comments
Enter text
Personal Protective Equipment (PPE)
Verify required PPE is used per OSHA 1926 Subpart E (1910 Subpart I in general industry) and ANSI Z49.1.
Welding Helmet/ShieldYesNo
Safety Glasses/GogglesYesNo
Welding GlovesYesNo
FR Protective ClothingYesNo
Proper Clothing FitYesNo
BootsYesNo
Hearing ProtectionYesNo
RespiratorYesNo
Comments
Enter text
Work Area & Fire Safety
Inspect area for fire hazards per OSHA 1926.352 (1910.252(a) in general industry) and NFPA 51B.
Combustibles Cleared Within 35 ft (or Shielded)YesNo
Floor CleanYesNo
Combustible Flooring ProtectedYesNo
Openings CoveredYesNo
Adjacent Areas SafeYesNo
No Flammable AtmosphereYesNo
Fire Sprinklers/Alarms ActiveYesNo
Fire Extinguisher ReadyYesNo
Correct Fire ExtinguisherYesNo
No Unauthorized AreaYesNo
Comments
Enter text
Welding Equipment Inspection
Verify safe setup and condition per OSHA 1926.350 and 1926.351 (1910.253 and 1910.254 in general industry).
Machine ConditionYesNo
Cables & Leads IntactYesNo
Frame GroundedYesNo
Electrode Holder SafeYesNo
Cylinders SecuredYesNo
No Leaks in HosesYesNo
Flashback ArrestorsYesNo
Screens in PlaceYesNo
Wet Conditions AddressedYesNo
Comments
Enter text
Ventilation and Fume Control
Ensure adequate ventilation per OSHA 1926.353 and 1926.354 (1910.252(c) in general industry) and 1910.134.
Adequate VentilationYesNo
Confined Space TestedYesNo
Ventilation ContinuousYesNo
Fume Source ControlYesNo
Respirator UsedYesNo
Coatings RemovedYesNo
Plume AvoidanceYesNo
Comments
Enter text
Fire Watch & Emergency Readiness
Verify fire watch and response readiness per OSHA 1926.352(e) (1910.252(a)(2)(iii) in general industry).
Fire Watch RequiredYesNo
Fire Watch AssignedYesNo
Fire Extinguisher ReadyYesNo
Understands DutiesYesNo
Knows Alarm ProcedureYesNo
Fire Watch ≥ 30 Min After Work (1 Hr per NFPA 51B)YesNo
Extended MonitoringYesNo
Adjacent Areas MonitoredYesNo
Comments
Enter text
Final Sign-off
All pre-work welding safety checklist items satisfactory?
YesNo
Pre-Work Safety Inspection Completed By
Enter text
Signature
Signed on the phone
Date & Time
Oct 14, 2026Select a date
Photo
Post-Work Completion Acknowledgment (Optional): The work area was monitored for the required cool-down period after welding, and no signs of fire or hazards remain.
YesNo
Final check performed by
Enter text
at (time)
Enter text
Signature
Signed on the phone
Submit
The digital form
Same checklist, on every phone on the job
Shows up when it’s due. Triggered by the job assignment, or at clock-in or clock-out. Nobody has to remember it.
Pre-filled before they start. Job, date and inspector fill in on their own, so the crew only answers the checks.
Photos and other media, attached. Snapped on the spot and saved with the answers they explain.
Never lose a form again. Every one is filed to the job the moment it’s sent. No data entry back at the office.
A spreadsheet with a dropdown for every answer, ready to fill in, sort and keep as a log.
Download Excel
How to use it
How to run the Welding Safety Checklist
01
Check it before the first start
Do it at the start of every shift, before the machine moves, with the operator who’ll run it.
02
Walk around, then test from the seat
Work through the 7 sections: fluids and the walk-around first, then controls, brakes and safety devices with it running.
03
A fail means it stays parked
Tag out anything that fails and report it to the shop or the super, with a photo. It doesn’t run until it’s fixed.
04
Sign it and keep it with the machine
The operator signs. Keep each day’s sheet with the machine, so the next operator and the inspector can see its history.
Why we built this
Most breakdowns give a warning first
A leak, a worn hose, brakes that feel soft. A few minutes at the start of the shift catches them before they cost a day of downtime, or someone’s safety.
Built for the field. Every check is written the way crews talk, with room for notes, photos and a signature.
Free, with no catch. No email, no account. Print it and hand it out.
On paper or on the phone. The same form runs on the Workyard app, filed to the job when it’s sent.
Workyard is the construction operations platform for specialty contractors and self-performing general contractors determined to grow without sacrificing job control or margins.
Forms like this one are what our customers’ crews fill in on Workyard every day, on the same app they clock in with.
workers on Workyard every day
100,000+
free templates, none of them gated
182
Forms & Workflows
Get every form back from every crew, every day
It shows up on its own. Attach it to a task, a job or clock-out, and it’s on the crew’s phone when it’s due.
It can’t be skipped. Make it required and the day can’t close until it’s in.
You see it the same day. Filed, flagged or missing, every job on one board, before anyone has to call.
7:02 AMToolbox talkMeridian Business ParkRay T. · 12 signaturesFiled to job
9:40 AMSite inspectionFairview Clinic · L2 eastDiego M. · 8 photosFiled to job
11:15 AMSite inspectionFairview Clinic · L2 westFirestop answered No at grid C-4Flagged · to the PM
2:14 PMPre-start checkMeridian Business ParkExcavator 3 · Dana C. · signedFiled to job
4:30 PMDaily logRiverside TowerDue at clock-outMissing
Fairview L2 west: firestop at C-4 answered No. Photo attached, PM notified at 11:15 AM. The ceiling stays open until it’s fixed, not a box ticked on a sheet in the truck.
Before welding begins, it is crucial to check that all required personal protective equipment (PPE) such as welding helmets, gloves, and flame-resistant clothing are in good condition and properly worn. Inspect gas lines and connections for leaks or damage to prevent hazardous gas exposure or fire risks. Additionally, ensure fire barriers or shields are in place to protect surrounding areas, verify adequate ventilation to control fumes, and confirm that welding tools and equipment are functioning correctly and safely.
Who fills out the welding safety checklist?
The welding safety checklist is typically completed by the welder performing the work or the designated safety supervisor on site. This person is responsible for verifying that all safety measures, equipment inspections, and environmental controls are in place before welding operations commence. Having a trained individual fill out the checklist ensures compliance with safety standards and helps prevent accidents.
Does OSHA require a hot work permit?
Yes, OSHA requires a hot work permit in many environments where welding, cutting, or brazing is performed, especially in areas with flammable or combustible materials. This permit system is designed to ensure that all safety precautions, such as fire watches and hazard assessments, are implemented before hot work begins. The National Fire Protection Association (NFPA) also mandates hot work permits to reduce fire risks during welding operations.
Why is ventilation important during welding?
Ventilation is essential during welding to prevent the accumulation of toxic fumes, gases, and vapors generated by the welding process. Proper ventilation maintains air quality by removing hazardous contaminants from the breathing zone, reducing the risk of respiratory illnesses and other health problems. Using local exhaust ventilation or working in well-ventilated areas helps protect welders and nearby workers from exposure to harmful substances.
Do I need a Workyard account to use it?
No. Print the paper form, save it as a PDF, or download the Word or Excel file, free, with no email and no sign-up. You only need an account to put the digital form on your crew’s phones.
Can I edit the template?
Yes. Download the Word or Excel version to add your logo, add checks from your project spec or remove sections you don’t need. They open in Google Docs and Google Sheets too.
How do I get my crew to fill it in on their phones?
Add the digital form to Workyard and attach it to the job or the task it belongs to. It shows up in the app your crew already clocks in with, and every form comes back signed, with its photos, filed to the job.