An above ceiling inspection is the check of everything that will be hidden over a ceiling (firestopping, sprinklers, wiring, ductwork and piping) once the trades are done up there and before the tiles go back in or the ceiling is closed. It gives the GC, the trades and the inspector one last look at work nobody will see again without pulling the ceiling apart. This above ceiling inspection checklist records that walk area by area, with photos and a list of what still needs fixing.

What is an above ceiling inspection checking for?

The inspection is checking that every trade left the space above the ceiling the way code and the drawings require, and that nobody broke someone else's work on the way out. A cable tray installer who cuts a fire collar, or an electrician who hangs conduit off a sprinkler pipe, creates a problem that's cheap to fix with the ceiling open and expensive once it's closed.

The checklist is grouped by system, each item marked Yes, No or N/A with notes and photos:

SectionWhat you check
Fire barriers and penetrationsRated firestop assemblies intact, fire collars on through-penetrations, joints sealed per the UL label, rated bulkheads and sleeves labeled
Sprinklers18 in clearance below heads, escutcheons flush, spray pattern clear, pipe hangers within code spacing
ElectricalJunction boxes accessible with covers on, conduit and cable supported, nothing supported from ceiling grid wires or sprinkler pipe, plenum-rated cable in plenums, no flexible cords in concealed plenum space, raceway penetrations firestopped
HVACDuct joints sealed with listed mastic, fire dampers labeled and operable, return-air paths clear, equipment supports secure and level
PlumbingPipe insulated where required, sleeves firestopped, shut-off valves labeled and operable, drains sloped and supported
Final assessmentTiles replaced or the area barricaded, photos taken of every open zone

How to fill out the checklist

  1. Enter the building, room or area, and whether the ceiling is open or closed.
  2. Walk one area at a time and work through each system. Shine a light along penetrations rather than glancing at them.
  3. Mark every No with a note and a photo that shows where it is.
  4. Move each No to the deficiency log: location, issue, action required, who is responsible, due date, and closed when it's done.
  5. Take photos of every open zone before it's closed. These are your record of what's above the ceiling.
  6. Sign off: the inspector, the project supervisor, and the AHJ or safety officer where they take part.

Hold the ceiling open until each deficiency is closed and re-checked. Running the walk with each trade's foreman present gets fixes assigned on the spot.

Commercial vs residential above ceiling inspections

Above ceiling inspections are mainly a commercial job: offices, schools, hospitals and retail spaces with accessible ceilings and return-air plenums, where many trades share the space above the grid. Some cities run their own above-ceiling inspection or permit step, so ask your building department what it requires on your job. In houses, ceilings are usually drywall and the same check happens before cover, using a pre-drywall inspection checklist.

The form lists the references its items come from: IBC §110.3.8 (the fire- and smoke-resistant penetration inspection in the 2021 IBC; the number differs in other editions), NEC (NFPA 70) 300.11, 300.21, 300.22, 314.29 and 400.12, NFPA 13, UL 1479 and OSHA 29 CFR 1926 Subpart X. Check the editions your jurisdiction has adopted.

Run it in Workyard or download it free

In Workyard, the checklist is a digital form your superintendent fills in on a phone on the ladder, with photos of each open zone and sign-offs on screen. A No can go straight to the person you name, who can pass it to the responsible trade, and every submission is filed to the job in the office, ready to export as PDF or CSV. See construction inspections in Workyard. Or download the free template as a PDF, Word or Excel file. More forms for this work are under commercial construction.