A pre drywall inspection checklist is the last look inside the walls before they're closed: framing, electrical, plumbing, HVAC, insulation and fire-blocking, all checked while everything is still visible. Builders, superintendents and remodelers use it to catch problems that would otherwise mean cutting open finished drywall, and to get each trade's sign-off before the drywall crew starts hanging.
What is a pre-drywall inspection?
A pre-drywall inspection is a walk of the whole house or unit after every rough-in is done and insulation is in, but before any board goes up. It is different from the rough-in inspections by the building department. Those check one trade at a time against code. The pre-drywall walk checks that all of it is finished, fits together and matches the plans, and the form's first framing item asks whether every rough-in inspection has already passed and been signed off.
Any No on the checklist has to be corrected and reinspected before drywall is released.
What to look for, trade by trade
Each section is a list of Yes, No or Notes items with its own photo upload.
- Framing and structure: rough-in inspections passed, stud spacing per plan, headers sized and bearing, hangers fully nailed, anchor bolts and straps, fire-blocking at floors, chases and tubs, shear panel nailing.
- Electrical rough-in: box depth flush with the future drywall face, cable secured near boxes and along runs, nail plates at stud penetrations, circuits labeled, smoke and CO detector wiring, low-voltage boxes roughed in.
- Plumbing and gas: drain slope, pipe supports, pressure test witnessed and logged, vents routed, penetrations sleeved and fire-caulked, gas line bonding and tracer wire.
- HVAC rough-in: ducts per plan, hanger spacing, refrigerant lines insulated, bath and combustion vents to the exterior, range hood duct path, condensate drains sloped and trapped.
- Insulation and air sealing: insulation complete, top plates and rim joists sealed, window and door gaps foamed, exterior penetrations caulked, vapor retarder where required.
- Safety and accessibility: blocking for stair rails and grab bars, egress window openings, attic access size, fire-rated walls protected.
Blocking is the item people regret most. Grab bars, TV mounts, heavy cabinets and stair rails all need solid wood behind the drywall, and adding it later means cutting the wall. Check for it room by room.
Problems go into the deficiency and action log: item and trade, issue, corrective action, responsible party, target date, a photo note and a close-out check. Then each lead signs: the inspector or code official, the superintendent, the electrical lead, the HVAC lead and the insulation contractor.
Codes the checklist is built on
Each section names the code it follows: IRC/IBC 2021 for framing, NEC 2023 for electrical, IPC, IMC and IFGC 2021 for plumbing, HVAC and gas, and the IECC for insulation and air sealing. Some items carry the numbers right on the form, such as drain slope of a quarter inch per foot for pipe up to 2½ inches and an eighth inch per foot for 3 to 6 inches. Your jurisdiction may have adopted different editions or local amendments, so check what applies before using the form on a permitted job. HVAC crews who want a closer check of their own work can run the HVAC rough-in inspection checklist first.
Get the pre drywall inspection checklist PDF
Download the pre drywall inspection checklist as a PDF, or as a Word or Excel file to add items from your own plans. It's free, with no sign-up. Want the same walk in a set order? See the walkthrough sequence version. On phones, Workyard's construction inspection app runs the checklist on the job: photos of each item, every lead signs on screen, any No goes to the person you name, who can pass it to the trade, and the finished checklist is filed to the job in the office and exports as a PDF for the owner or lender.