An air balance report template is the form a balancing technician uses to record measured airflow and water flow on an HVAC system against the design values, along with the adjustments made to bring them in line. Mechanical contractors, TAB technicians and commissioning teams use it on new buildings, renovations and existing systems that aren't heating or cooling the way they should.

The form covers both sides of the job: air (fans, supply and return, every outlet) and water (pumps, loops, coils). That is why it is called an air and water balance report rather than an air balance report alone.

What an HVAC test and balance report records

An HVAC test and balance report records what the system actually delivers compared with what the engineer designed, outlet by outlet and coil by coil. The three terms people search for (air balance report, test and balance report, TAB report) belong to the same family. The full TAB report covers testing, adjusting and balancing both air and water; an air balance report covers the air side only.

The report is the proof that a system was set up to design. It goes to the engineer of record, the owner and the commissioning agent, and on many commercial jobs a balanced system has to be shown before the building is occupied.

Who prepares a test and balance report, and when

On commercial work, the project specs usually name who may do the balancing and which format the final report follows. Specs often call for a balancer certified by one of the recognized bodies, such as AABC, NEBB, NBC or TABB, and require their report forms. This template is a field form for recording readings as you go; on a spec job, the readings then go into the certified report the spec calls for. On smaller and residential jobs, the field form is often the report.

Balancing happens at a few points in a building's life:

  • New construction, after the system is installed and running, before turnover.
  • Renovations and tenant fit-outs, when ductwork, terminals or equipment change.
  • Existing buildings, when occupants complain about hot and cold spots or equipment is replaced.
  • Maintenance audits, to check a system hasn't drifted from its last balance.

What's in the air balance report template

Project and system details

Project name and location, date and time of the test, new or existing construction, commercial or residential, the system or zone being tested, and the operating mode during the test: cooling, heating or both.

Test instruments and conditions

The air measurement method (flow hood, anemometer traverse, Pitot tube traverse or velometer), the primary instrument with its serial number and last calibration date, ambient air temperature and site altitude. A separate note covers the instrument used for water balancing, with room for photos of calibration labels. Readings from an instrument without a current calibration date are the first thing a reviewer will question.

Air balancing measurements

For the air handler: unit ID, design and measured supply airflow, design and measured return airflow in CFM, fan speed, external static pressure, and fan motor amps against nameplate full-load amps. Then an outlet table: each outlet's location or ID, design CFM, measured CFM, percent of design, whether it falls within ±10%, and notes. The section closes with zone totals, overall percent of design, and supply and return air temperatures.

Hydronic balancing measurements

For each pump or loop: design and measured flow in GPM, discharge, suction and differential pressure, and pump motor amps. Then a coil and branch table with design GPM, measured GPM, percent of design and the ±10% check, followed by supply and return water temperatures.

Adjustments, comments and sign-off

What you adjusted, recommendations, and photos of issues or final settings. The technician signs, and a supervisor or engineer signs to verify.

Reading percent of design

Percent of design is measured flow divided by design flow, times 100. It tells you at a glance which outlets or coils are starved and which are getting too much. Here is a short worked example:

OutletDesign CFMMeasured CFM% of designWithin ±10%?
Office 101 supply20018492%Yes
Office 102 supply20015276%No, open damper and retest
Conference supply 1350392112%No, close damper and retest

The form uses ±10% of design as its check, a common target. The tolerance that counts is the one in your project specs, which may be tighter or looser, so check before you mark anything as passing.

How to fill in the air balance report

  1. Fill in the project and system details and set the system to the mode you're testing.
  2. Record your instruments with serial numbers and calibration dates before taking any readings.
  3. Take the air handler readings first: airflow, fan speed, static pressure and motor amps.
  4. Measure every outlet and record design, measured and percent of design.
  5. Adjust dampers, then measure again. Record readings before and after adjustment so the report shows the work.
  6. Repeat for the water side: pump, loops, then each coil or branch.
  7. Write down what you changed and anything you couldn't fix, then sign and send it for verification.

Problems the readings point to

Balancing reports regularly turn up the same handful of issues. Each one should go in the recommendations box with the reading that shows it:

  • Motors running over nameplate full-load amps.
  • More outside air than the design calls for.
  • Static pressure set higher than the system needs.
  • Balancer readings that don't match the building controls.
  • Outlets or coils that can't reach design even with dampers or valves wide open, which often points to a duct, piping or equipment problem rather than a balancing one.

Recording balance readings on a phone

On paper, readings get written on a clipboard, typed into a spreadsheet later and checked by someone who wasn't there. In Workyard, the technician fills in the air and water balance report on their phone at the unit, attaches photos of calibration labels and final settings, and signs on screen. The supervisor or engineer can sign on the same screen, and each submitted report is saved against the job. See forms and workflows in Workyard, or read about Workyard for HVAC and mechanical contractors.

Related forms: the HVAC commissioning checklist, the HVAC control systems commissioning log and the HVAC inspection checklist for service visits.

Get the free air and water balance report

Download the air and water balance report free as a PDF to print, a Word document to edit, or an Excel sheet to keep readings for every system in one file. No sign-up. Add your company details and your project's tolerance, and use the same version on every system you balance.