Confirm preparatory steps and prior approvals, as typically required before insulating or before covering insulation.
Permits and approved plans available?YesNoN/A
Plans reviewed to confirm insulation requirements?YesNoN/A
Previous required inspections signed off?YesNoN/A
Area is Dried-In?YesNoN/A
Code Reference CheckYesNoN/A
Safety Precautions (OSHA Compliance)
Before proceeding, confirm that the inspection can be performed safely, following relevant OSHA guidelines for construction work. If the answer to any of these questions is "No", pause the inspection until safety requirements are met.
PPE in place and in appropriate condition?YesNoN/A
Work Area Safe?YesNoN/A
Work area offers sufficient heat source clearance?YesNoN/A
Exterior Wall Insulation Inspection
Wall Insulation Type
Select an option
Installed R-Value (Walls)
Enter text
Insulation Thickness (inches)
Enter text
Wall insulation details
Coverage Complete (Walls)YesNoN/A
Proper Fit and SealingYesNoN/A
No Compression or DamageYesNoN/A
Vapor Retarder Installed (Walls)YesNoN/A
Fire Blocking at WallsYesNoN/A
Thermal Barrier Installed or Planned Over Foam Plastic (IRC R316.4)YesNoN/A
Wall Insulation Photo
Ceiling/Attic Insulation Inspection
Ceiling Insulation Type
Select an option
Installed R-Value (Ceiling)
Enter text
Insulation Depth (Attic) in inches
Enter text
Roof insulation details
Coverage Complete (Ceiling)YesNoN/A
No Gaps or VoidsYesNoN/A
No CompressionYesNoN/A
Eave Baffles InstalledYesNoN/A
Recessed Light ClearanceYesNoN/A
Attic Access Hatch InsulatedYesNoN/A
Attic Markers Present Where AppropriateYesNoN/A
Ceiling Vapor Barrier Properly InstalledYesNoN/A
Foam Plastic Covered by Thermal or Ignition Barrier (IRC R316.4, R316.5.3)YesNoN/A
Ceiling Insulation Photos
Floor and Crawlspace Insulation Inspection
Floor Insulation Type
Select an option
Installed R-Value (Floor)
Enter text
Insulation Thickness (in inches)
Enter text
Floor Insulation Details
Coverage CompleteYesNoN/A
Insulation SupportedYesNoN/A
No Gaps or CompressionYesNoN/A
Has Appropriate Ventilation ClearancesYesNoN/A
Floor Vapor Barrier Properly InstalledYesNoN/A
Floor Insulation Photo
Crawlspace Insulation Location: How is the crawlspace insulated?
Does the insulation installation meet project requirements and appear code-compliant?YesNo
Were any issues or deficiencies found that require correction?YesNo
Signature and Project Details
Project ID / Location
Enter text
Inspector Name
Enter text
Inspection Date
Select a date
Inspector Signature
Sign here
Submit
Scroll through the form
The template
The full Insulation Inspection Report
Print it for the clipboard, or put it on your crew’s phones. Same 34 checks either way.
Your logo
Insulation Inspection Report
Verify insulation installation quality and code compliance with this detailed inspection form. Check R-values, gaps, vapor barriers, and fire blocking before walls are sealed, avoiding costly rework and ensuring proper energy efficiency.
Job
Date
1 · Pre-Inspection Verification
1 · Pre-Inspection Verification
Y
N
N/A
1.1
Permits and approved plans available?
1.2
Plans reviewed to confirm insulation requirements?
1.3
Previous required inspections signed off?
1.4
Area is Dried-In?
1.5
Code Reference Check
2 · Safety Precautions (OSHA Compliance)
2 · Safety Precautions (OSHA Compliance)
Y
N
N/A
2.1
PPE in place and in appropriate condition?
2.2
Work Area Safe?
2.3
Work area offers sufficient heat source clearance?
Crawlspace Insulation Location: How is the crawlspace insulated?Floor above crawlspace (vented crawl – insulation in joists above)Crawlspace walls (unvented/sealed crawl – insulation on interior foundation walls)Uninsulated/Not applicable
Does the insulation installation meet project requirements and appear code-compliant?
6.2
Were any issues or deficiencies found that require correction?
7 · Signature and Project Details
Project ID / Location
Inspector Name
Inspection Date
Name
Signature
Date
Insulation Inspection Report on a phone
Insulation Inspection Report
Job *
26-104 Riverside DuplexesSelect a job
Oct 14, 8:12 AM26-104 Riverside Duplexes
Pre-Inspection Verification
Confirm preparatory steps and prior approvals, as typically required before insulating or before covering insulation.
Permits and approved plans available?YesNoN/A
Plans reviewed to confirm insulation requirements?YesNoN/A
Previous required inspections signed off?YesNoN/A
Area is Dried-In?YesNoN/A
Code Reference CheckYesNoN/A
Safety Precautions (OSHA Compliance)
Before proceeding, confirm that the inspection can be performed safely, following relevant OSHA guidelines for construction work. If the answer to any of these questions is "No", pause the inspection until safety requirements are met.
PPE in place and in appropriate condition?YesNoN/A
Work Area Safe?YesNoN/A
Work area offers sufficient heat source clearance?YesNoN/A
Exterior Wall Insulation Inspection
Wall Insulation Type
Fiberglass battsSelect an option
Installed R-Value (Walls)
Enter text
Insulation Thickness (inches)
Enter text
Wall insulation details
Coverage Complete (Walls)YesNoN/A
Proper Fit and SealingYesNoN/A
No Compression or DamageYesNoN/A
Vapor Retarder Installed (Walls)YesNoN/A
Fire Blocking at WallsYesNoN/A
Thermal Barrier Installed or Planned Over Foam Plastic (IRC R316.4)YesNoN/A
Wall Insulation Photo
Ceiling/Attic Insulation Inspection
Ceiling Insulation Type
Blown-in fiberglassSelect an option
Installed R-Value (Ceiling)
Enter text
Insulation Depth (Attic) in inches
Enter text
Roof insulation details
Coverage Complete (Ceiling)YesNoN/A
No Gaps or VoidsYesNoN/A
No CompressionYesNoN/A
Eave Baffles InstalledYesNoN/A
Recessed Light ClearanceYesNoN/A
Attic Access Hatch InsulatedYesNoN/A
Attic Markers Present Where AppropriateYesNoN/A
Ceiling Vapor Barrier Properly InstalledYesNoN/A
Foam Plastic Covered by Thermal or Ignition Barrier (IRC R316.4, R316.5.3)YesNoN/A
Ceiling Insulation Photos
Floor and Crawlspace Insulation Inspection
Floor Insulation Type
Fiberglass battsSelect an option
Installed R-Value (Floor)
Enter text
Insulation Thickness (in inches)
Enter text
Floor Insulation Details
Coverage CompleteYesNoN/A
Insulation SupportedYesNoN/A
No Gaps or CompressionYesNoN/A
Has Appropriate Ventilation ClearancesYesNoN/A
Floor Vapor Barrier Properly InstalledYesNoN/A
Floor Insulation Photo
Crawlspace Insulation Location: How is the crawlspace insulated?
Floor above crawlspace (vented crawl – insulation in joists above)Select an option
A spreadsheet with a dropdown for every answer, ready to fill in, sort and keep as a log.
Download Excel
How to use it
How to run the Insulation Inspection Report
01
Run it before the work is covered
Walk it before the next trade closes things up or the area is handed over, and again after any fix. Fill in the header first so the record stands on its own.
02
Work the sections in order
Go through the 7 sections in order so nothing gets skipped. Answer every check: a blank isn’t an answer.
03
Every miss gets a photo and an owner
Write down what’s wrong, take a photo and name the trade that owns the fix, with a date.
04
Re-check, sign, then release
Walk the misses again once they’re fixed. Sign it off, and only then let the area close.
Why we built this
An inspection only counts if it’s written down
A miss found before the work is covered up is a quick fix. Found after, it’s a tear-out, a failed inspection and a schedule hit. The written record is how you prove the check happened.
Built for the field. Every check is written the way crews talk, with room for notes, photos and a signature.
Free, with no catch. No email, no account. Print it and hand it out.
On paper or on the phone. The same form runs on the Workyard app, filed to the job when it’s sent.
Workyard is the construction operations platform for specialty contractors and self-performing general contractors determined to grow without sacrificing job control or margins.
Forms like this one are what our customers’ crews fill in on Workyard every day, on the same app they clock in with.
workers on Workyard every day
100,000+
free templates, none of them gated
182
Forms & Workflows
Get every form back from every crew, every day
It shows up on its own. Attach it to a task, a job or clock-out, and it’s on the crew’s phone when it’s due.
It can’t be skipped. Make it required and the day can’t close until it’s in.
You see it the same day. Filed, flagged or missing, every job on one board, before anyone has to call.
7:02 AMToolbox talkMeridian Business ParkRay T. · 12 signaturesFiled to job
9:40 AMSite inspectionFairview Clinic · L2 eastDiego M. · 8 photosFiled to job
11:15 AMSite inspectionFairview Clinic · L2 westFirestop answered No at grid C-4Flagged · to the PM
2:14 PMPre-start checkMeridian Business ParkExcavator 3 · Dana C. · signedFiled to job
4:30 PMDaily logRiverside TowerDue at clock-outMissing
Fairview L2 west: firestop at C-4 answered No. Photo attached, PM notified at 11:15 AM. The ceiling stays open until it’s fixed, not a box ticked on a sheet in the truck.
Inspect insulation after it is installed and before drywall or other finishes cover it. Many jurisdictions that use the IRC or IECC require an insulation inspection at this stage, and it is the last chance to fix gaps, compression and missing vapor retarders. Re-inspect any area that is repaired or reworked before it is closed up.
What should I look for when inspecting insulation?
When inspecting insulation, look for signs of damage or deterioration such as discoloration or damage to the outer jacketing, loose or missing insulation, and any areas where insulation has been removed but not replaced. Check for unsealed penetrations, sagging, or pulling away of jacketing from pipes or supports, and signs of moisture, such as ice, mold, mildew, or condensation on the insulation surface. Also, watch for “hot spots” that might indicate insulation failure and ensure expansion or contraction joints are functioning properly. Additionally, verify that all specified areas are insulated according to the project requirements, including fittings, valves, and equipment. Confirm that insulation materials are approved and properly installed, with seams sealed and vapor barriers intact. Check that metal sheathing, where required, is correctly applied with moisture barrier seam locks, and ensure insulation is secured to prevent contact with vents or other heat sources. Mark any alterations or repairs on as-built drawings for recordkeeping.
Does this form apply to commercial projects?
Yes, this Insulation Inspection Report can be used for both residential and commercial projects. While specific insulation requirements may vary based on building type, occupancy, and local codes, the core elements, such as verifying R-values, proper installation, vapor barriers, and fire blocking, are essential across all project types. For commercial buildings, the form can be adapted to include areas like mechanical rooms, flat roof assemblies, metal framing, or specialized insulation systems.
Is this form required by code?
An Insulation Inspection Report isn’t always required as a formal document. But the inspection itself is a key part of meeting building code. Most jurisdictions, especially those following the International Residential Code (IRC) or International Energy Conservation Code (IECC), require insulation to be inspected before it’s covered by drywall or finishes. This ensures it meets proper R-value, coverage, and installation standards. In commercial settings, insulation inspections help confirm compliance with stricter energy codes, such as ASHRAE 90.1, and are often tied to permitting or energy efficiency certifications. While inspectors may not ask for a specific report form, having one ready can simplify approvals, reduce rework, and help you clearly document that the job meets code requirements.
Do I need a Workyard account to use it?
No. Print the paper form, save it as a PDF, or download the Word or Excel file, free, with no email and no sign-up. You only need an account to put the digital form on your crew’s phones.
Can I edit the template?
Yes. Download the Word or Excel version to add your logo, add checks from your project spec or remove sections you don’t need. They open in Google Docs and Google Sheets too.
How do I get my crew to fill it in on their phones?
Add the digital form to Workyard and attach it to the job or the task it belongs to. It shows up in the app your crew already clocks in with, and every form comes back signed, with its photos, filed to the job.