Are the following in place and clearly visible on site?
Job address posted on-siteYesNo
Permit and approved plans availableYesNo
Permit information accurateYesNo
All fixtures listed and approvedYesNo
Licensed plumber listed on permit (or homeowner verified)YesNo
DWV System Inspection
Are all DWV components correctly installed and tested?
Piping slope and size per fixture unit countYesNo
Vents installed downstream of trapsYesNo
Approved test performed (10-ft head or 5 psi air, 15 min)YesNo
Back-to-back fixtures use approved fittingsYesNo
Pipe transitions maintain sweep and clearanceYesNo
Proper trap arms, cleanouts, and vent terminationsYesNo
Water Supply Inspection
Confirm the following water supply conditions
Water piping size and material per codePassFail
Pressure tested with water at not less than working pressure, or 50 psi air (not permitted for plastic pipe)PassFail
Main shutoff valve and backflow preventers installedPassFail
Water hammer arrestors where quick-close valves are usedPassFail
Hot/cold lines protected from freezing and properly insulatedPassFail
Pipe supports, penetrations, and nail plates installed correctlyPassFail
Underground Piping & Protection
Are these underground conditions met?
Pipes not directly embedded in concretePassFail
Voids and sleeves used at concrete penetrationsPassFail
Pipes laid on firm beddingPassFail
Water service buried below frost linePassFail
Tracer wire installed with plastic pipingPassFail
Copper joints brazed if under slabPassFail
Cleanouts and Venting
Do venting and cleanout systems meet code?
Cleanouts accessible with correct clearancePassFail
Proper slope and orientation of vent pipesPassFail
Vents extend minimum 6" above rooflinePassFail
Vent distances per fixture type are compliantPassFail
Island venting uses loop and cleanout correctlyPassFail
AAVs used only if approved by local codePassFail
Support and Protection of Pipes
Are support and protection measures in place?
Pipes supported per UPC Table 313.3PassFail
Nail plates used within 1" of framing facePassFail
Hangers don’t damage or restrict pipe movementPassFail
Sleeves used for masonry/concrete penetrationsPassFail
Vertical and horizontal supports meet spacing rulesPassFail
Project Details
Project Name
Enter text
Project Address
Enter text
Permit Number
Enter text
Project Type
Select an option
Inspection Date & Time
Select a date
Inspector/Installer Name
Enter text
Inspector License #
Enter text
Company / Contractor
Enter text
Final Review & Sign-Off
Overall Rough-In Status
Select an option
Inspector’s Comments
Enter text
Photo Attachments
Installer/Inspector Signature
Sign here
Date
Select a date
Supervisor/Reviewer Signature
Sign here
Date
Select a date
Submit
Scroll through the form
The template
The full Plumbing Rough-In Inspection
Print it for the clipboard, or put it on your crew’s phones. Same 34 checks either way.
Your logo
Plumbing Rough-In Inspection
This smart form helps verify DWV and water supply line installation before cover-up to catch issues early and improve compliance with international plumbing codes.
Job
Date
1 · Permits and Plans
1 · Permits and Plans
Y
N
Note(s)
1.1
Job address posted on-site
1.2
Permit and approved plans available
1.3
Permit information accurate
1.4
All fixtures listed and approved
1.5
Licensed plumber listed on permit (or homeowner verified)
2 · DWV System Inspection
2 · DWV System Inspection
Y
N
Note(s)
2.1
Piping slope and size per fixture unit count
2.2
Vents installed downstream of traps
2.3
Approved test performed (10-ft head or 5 psi air, 15 min)
2.4
Back-to-back fixtures use approved fittings
2.5
Pipe transitions maintain sweep and clearance
2.6
Proper trap arms, cleanouts, and vent terminations
3 · Water Supply Inspection
3 · Water Supply Inspection
Pass
Fail
Note(s)
3.1
Water piping size and material per code
3.2
Pressure tested with water at not less than working pressure, or 50 psi air (not permitted for plastic pipe)
3.3
Main shutoff valve and backflow preventers installed
3.4
Water hammer arrestors where quick-close valves are used
3.5
Hot/cold lines protected from freezing and properly insulated
3.6
Pipe supports, penetrations, and nail plates installed correctly
4 · Underground Piping & Protection
4 · Underground Piping & Protection
Pass
Fail
Note(s)
4.1
Pipes not directly embedded in concrete
4.2
Voids and sleeves used at concrete penetrations
4.3
Pipes laid on firm bedding
4.4
Water service buried below frost line
4.5
Tracer wire installed with plastic piping
4.6
Copper joints brazed if under slab
5 · Cleanouts and Venting
5 · Cleanouts and Venting
Pass
Fail
Note(s)
5.1
Cleanouts accessible with correct clearance
5.2
Proper slope and orientation of vent pipes
5.3
Vents extend minimum 6" above roofline
5.4
Vent distances per fixture type are compliant
5.5
Island venting uses loop and cleanout correctly
5.6
AAVs used only if approved by local code
6 · Support and Protection of Pipes
6 · Support and Protection of Pipes
Pass
Fail
Note(s)
6.1
Pipes supported per UPC Table 313.3
6.2
Nail plates used within 1" of framing face
6.3
Hangers don’t damage or restrict pipe movement
6.4
Sleeves used for masonry/concrete penetrations
6.5
Vertical and horizontal supports meet spacing rules
7 · Project Details
Project Name
Project Address
Permit Number
Project TypeResidentialCommercial
Inspection Date & Time
Inspector/Installer Name
Inspector License #
Company / Contractor
8 · Final Review & Sign-Off
Overall Rough-In StatusPASS – Rough-In Approved for CoverFAIL – Corrections Required Before Covering
Inspector’s Comments
Photo Attachments · photo refs
Name
Signature
Date
Date
Name
Signature
Date
Date
Plumbing Rough-In Inspection on a phone
Plumbing Rough-In Inspection
Job *
26-104 Riverside DuplexesSelect a job
Oct 14, 8:12 AM26-104 Riverside Duplexes
Permits and Plans
Are the following in place and clearly visible on site?
Job address posted on-siteYesNo
Permit and approved plans availableYesNo
Permit information accurateYesNo
All fixtures listed and approvedYesNo
Licensed plumber listed on permit (or homeowner verified)YesNo
DWV System Inspection
Are all DWV components correctly installed and tested?
Piping slope and size per fixture unit countYesNo
Vents installed downstream of trapsYesNo
Approved test performed (10-ft head or 5 psi air, 15 min)YesNo
Back-to-back fixtures use approved fittingsYesNo
Pipe transitions maintain sweep and clearanceYesNo
Proper trap arms, cleanouts, and vent terminationsYesNo
Water Supply Inspection
Confirm the following water supply conditions
Water piping size and material per codePassFail
Pressure tested with water at not less than working pressure, or 50 psi air (not permitted for plastic pipe)PassFail
Main shutoff valve and backflow preventers installedPassFail
Water hammer arrestors where quick-close valves are usedPassFail
Hot/cold lines protected from freezing and properly insulatedPassFail
Pipe supports, penetrations, and nail plates installed correctlyPassFail
Underground Piping & Protection
Are these underground conditions met?
Pipes not directly embedded in concretePassFail
Voids and sleeves used at concrete penetrationsPassFail
Pipes laid on firm beddingPassFail
Water service buried below frost linePassFail
Tracer wire installed with plastic pipingPassFail
Copper joints brazed if under slabPassFail
Cleanouts and Venting
Do venting and cleanout systems meet code?
Cleanouts accessible with correct clearancePassFail
Proper slope and orientation of vent pipesPassFail
Vents extend minimum 6" above rooflinePassFail
Vent distances per fixture type are compliantPassFail
Island venting uses loop and cleanout correctlyPassFail
AAVs used only if approved by local codePassFail
Support and Protection of Pipes
Are support and protection measures in place?
Pipes supported per UPC Table 313.3PassFail
Nail plates used within 1" of framing facePassFail
Hangers don’t damage or restrict pipe movementPassFail
Sleeves used for masonry/concrete penetrationsPassFail
Vertical and horizontal supports meet spacing rulesPassFail
Project Details
Project Name
Enter text
Project Address
Enter text
Permit Number
Enter text
Project Type
ResidentialSelect an option
Inspection Date & Time
Oct 14, 2026Select a date
Inspector/Installer Name
Enter text
Inspector License #
Enter text
Company / Contractor
Enter text
Final Review & Sign-Off
Overall Rough-In Status
PASS – Rough-In Approved for CoverSelect an option
Inspector’s Comments
Enter text
Photo Attachments
Installer/Inspector Signature
Signed on the phone
Date
Oct 14, 2026Select a date
Supervisor/Reviewer Signature
Signed on the phone
Date
Oct 14, 2026Select a date
Submit
The digital form
Same checklist, on every phone on the job
Shows up when it’s due. Triggered by the job assignment, or at clock-in or clock-out. Nobody has to remember it.
Pre-filled before they start. Job, date and inspector fill in on their own, so the crew only answers the checks.
Photos and other media, attached. Snapped on the spot and saved with the answers they explain.
Never lose a form again. Every one is filed to the job the moment it’s sent. No data entry back at the office.
A spreadsheet with a dropdown for every answer, ready to fill in, sort and keep as a log.
Download Excel
How to use it
How to run the Plumbing Rough-In Inspection
01
Run it before the work is covered
Walk it before the next trade closes things up or the area is handed over, and again after any fix. Fill in the header first so the record stands on its own.
02
Work the sections in order
Go through the 8 sections in order so nothing gets skipped. Answer every check: a blank isn’t an answer.
03
Every miss gets a photo and an owner
Write down what’s wrong, take a photo and name the trade that owns the fix, with a date.
04
Re-check, sign, then release
Walk the misses again once they’re fixed. Sign it off, and only then let the area close.
Why we built this
An inspection only counts if it’s written down
A miss found before the work is covered up is a quick fix. Found after, it’s a tear-out, a failed inspection and a schedule hit. The written record is how you prove the check happened.
Built for the field. Every check is written the way crews talk, with room for notes, photos and a signature.
Free, with no catch. No email, no account. Print it and hand it out.
On paper or on the phone. The same form runs on the Workyard app, filed to the job when it’s sent.
Workyard is the construction operations platform for specialty contractors and self-performing general contractors determined to grow without sacrificing job control or margins.
Forms like this one are what our customers’ crews fill in on Workyard every day, on the same app they clock in with.
workers on Workyard every day
100,000+
free templates, none of them gated
182
Forms & Workflows
Get every form back from every crew, every day
It shows up on its own. Attach it to a task, a job or clock-out, and it’s on the crew’s phone when it’s due.
It can’t be skipped. Make it required and the day can’t close until it’s in.
You see it the same day. Filed, flagged or missing, every job on one board, before anyone has to call.
7:02 AMToolbox talkMeridian Business ParkRay T. · 12 signaturesFiled to job
9:40 AMSite inspectionFairview Clinic · L2 eastDiego M. · 8 photosFiled to job
11:15 AMSite inspectionFairview Clinic · L2 westFirestop answered No at grid C-4Flagged · to the PM
2:14 PMPre-start checkMeridian Business ParkExcavator 3 · Dana C. · signedFiled to job
4:30 PMDaily logRiverside TowerDue at clock-outMissing
Fairview L2 west: firestop at C-4 answered No. Photo attached, PM notified at 11:15 AM. The ceiling stays open until it’s fixed, not a box ticked on a sheet in the truck.
More site inspections templates
Free templates for the rest of the job
Ceiling Grid Installation Inspection
Grid LayoutYNN/A
Main runners spaced per project (typically 48″ o.c.)
Cross tees centered in openings & openings aligned
The standard plumbing rough-in includes installing drain, waste, vent (DWV) lines and water supply lines before walls or floors are closed. Pipes must be correctly sized, sloped, supported, and pressure-tested according to IRC, IPC, or UPC requirements before the official inspection.
What do inspectors look for during a plumbing rough-in inspection?
Inspectors verify correct pipe sizes, slopes, vent placements, cleanout accessibility, and proper support. They also check whether pressure tests pass per code, confirm traps and pipe materials are correct, and ensure DWV and water lines have required clearances and protection before concealment.
How do you pass a rough-in plumbing inspection?
To pass, ensure all plumbing is installed to code, pressure tests hold for the required duration (such as a 10-ft water head for DWV or 80 psi for water lines), and vents, cleanouts, and traps are properly placed. Using a checklist to self-inspect before scheduling helps prevent failures.
When should you schedule a plumbing rough-in inspection?
Schedule the inspection once all DWV and water supply piping is installed and pressure-tested, but before drywall, concrete, or flooring is added. Scheduling too early or too late can lead to delays, failed inspections, or costly rework.
Do I need a Workyard account to use it?
No. Print the paper form, save it as a PDF, or download the Word or Excel file, free, with no email and no sign-up. You only need an account to put the digital form on your crew’s phones.
Can I edit the template?
Yes. Download the Word or Excel version to add your logo, add checks from your project spec or remove sections you don’t need. They open in Google Docs and Google Sheets too.
How do I get my crew to fill it in on their phones?
Add the digital form to Workyard and attach it to the job or the task it belongs to. It shows up in the app your crew already clocks in with, and every form comes back signed, with its photos, filed to the job.