A pre drywall walkthrough checklist is the room-by-room check a superintendent, builder or inspector does after framing, rough-ins and insulation are done, and before anything gets covered. Once the board is up, a missing nail plate, an unsleeved pipe or a gap in the fire-blocking turns into a cut-out and a patch.

What is a pre-drywall inspection?

It is the last chance to see the inside of the walls. The pre-drywall inspection confirms the framing, wiring, plumbing, ductwork, fire-blocking, insulation and air sealing are complete and correct, and that the required rough-in inspections have passed. On new homes, buyers often ask for a pre drywall walk through of their own at this stage, which this checklist also suits.

How the pre drywall walkthrough checklist runs

The form is built around the order you walk, so nothing gets skipped:

  1. Project details: lot or project number, building or unit, weather and the trades on site.
  2. Exterior perimeter: each side of the building (front, right, rear, left) for anchor bolts and sill plates, visible shear-panel nailing, and window and door openings level and flashed.
  3. Main-floor rooms: finish each room before moving on.
  4. Stairs and vertical shafts: guard and handrail blocking, fire-blocking at shaft walls, smoke and CO rough wiring.
  5. Upper-floor rooms: the same room checks as the main floor.
  6. Attic and roof spaces: truss bracing and collar ties, bath and kitchen vents ending outside, insulation baffles, fire-blocking at top plates, refrigerant lines insulated and supported.
  7. Plumbing, gas and rough-in inspections: building, electrical, plumbing and mechanical rough-ins passed and signed, pressure test witnessed, drain slope and supports, gas piping supported and CSST bonded.
  8. Safety and accessibility: egress window openings, grab-bar and guardrail backing, attic access size.

What to look for in each room

ItemWhat a pass looks like
Stud spacing, headers and bearingMatches the plans, no cut or notched members left unrepaired
ElectricalBoxes set at the right depth, cable stapled, nail plates where cable passes near the stud face
PlumbingPenetrations sleeved and sealed
HVACSupply and return boots in place and secured
Fire-blockingInstalled at tubs and chases
Insulation and air sealingBatts fill the cavity, top plates and exterior penetrations sealed

Logging fixes and releasing drywall

Every No goes into the deficiency log with the trade, the issue, the fix, who owns it, the target date, a photo note and whether it is closed. The status is Pass, Conditional Pass or Fail, and any No has to be corrected and re-inspected before drywall is released. The inspector or code official, superintendent, electrical lead, HVAC lead and insulation contractor each sign. For a shorter check without the walk order, use the standard pre-drywall inspection checklist.

Run it in Workyard or download it

In Workyard the walkthrough opens on the super's phone on the job, with photos in each section and signatures taken on screen from each trade lead. Any No goes to the person you name, and the finished walkthrough is filed to the job in the office. See the construction inspection app and more drywall templates. The checklist is also free as a PDF, Word or Excel file.