A subcontractor daily report template gives a sub's foreman one page to tell the GC what their crew did today: who worked and for how many hours, what equipment ran, what materials came in or went up, what held them up, any safety incidents, the weather and photos. Electrical, plumbing, HVAC, carpentry, concrete and drywall subs send it at the end of each shift, and the GC folds it into its own daily log.

What goes in a subcontractor daily report

A useful subcontractor daily report answers the questions the GC's superintendent would otherwise call you about. This template has six sections.

SectionWhat you record
Labor summaryWork performed today, workers on site, total man-hours, and a crew breakdown by trade with count and hours
Equipment and materialsEquipment on site (crane, excavator, forklift, generator and others) with count and hours, materials used or delivered, any delays by cause, and delay details
Safety and housekeepingReportable incidents and whether OSHA was notified, minor accidents or near misses, hazard categories seen, housekeeping rated good, fair or poor
WeatherConditions, minimum and maximum temperature, site dry, wet, muddy or icy
PhotosConditions, completed work and problems
Final reviewSubcontractor name, trade, job name and location, supervisor, date and signature

Describe work performed by area and quantity, the same way it appears on your schedule of values: "Pulled wire, level 3, units 301 to 308" or "Set 14 rooftop curbs, east roof". That's the line that backs up your next pay application.

How often to complete the subcontractor daily report template

Complete it every day your crew is on site, and send it the same day. A report written on Friday for the whole week loses the detail that makes it useful, like the exact hours lost waiting on another trade. If your crew isn't on site but was scheduled to be, a short report saying why is worth sending too. Check your subcontract: many GCs set the deadline and the format, and some hold payment until reports are in.

Record delays so they count

The delay checkboxes cover weather, equipment breakdown, permit or inspection delay, material shortage, labor shortage and design change. Tick the cause, then use the delay details to say how many hours were lost and who you told. "Waited 3 hours for drywall sub to clear corridor B, told GC superintendent at 9:15" is the kind of entry that settles a backcharge argument months later. A photo of the blocked area makes it stronger.

The safety section

The form notes the OSHA rule at 29 CFR 1904.39: employers must report a work-related fatality within 8 hours and an in-patient hospitalization, amputation or loss of an eye within 24 hours. Check the current rule. Mark whether anything reportable happened and whether it was reported, then record near misses and hazards by category. A full incident write-up goes on its own form, such as the quality incident report for workmanship problems or your injury report for people.

The GC's side of the day goes on the general contractor daily log. More forms are under daily reporting templates.

Run it in Workyard or download it free

In Workyard, the subcontractor daily report is a digital form your foreman fills in on a phone before clocking out, with photos and a signature on screen. A reportable incident can go straight to a named person, and every report is filed to the job in the office, ready to export as PDF or CSV. See daily reporting in Workyard. Or download the free template as a PDF, Word or Excel file.