A demolition JHA is the hazard analysis and pre-demo checklist a superintendent or competent person fills in before a teardown starts and keeps updating until the site is cleared. It confirms the engineering survey, permits and utility cutoffs, asbestos and lead work, the fire and public protection plan, bracing and drop zones, and debris handling, then records deficiencies and gets the crew to sign that they were briefed. GCs, demolition and earthwork contractors, remodelers and site prep crews use it on everything from interior strip-outs to full structure demolition.

What is a demolition JHA?

A job hazard analysis takes a job, names its hazards and sets a control for each before work starts. A demolition JSA (job safety analysis) is the same thing under another name. Demolition needs its own version because the risks change as the structure comes down: walls lose support, floors get loaded with debris, hidden asbestos or live utilities turn up, and the public is often a few feet away. The form treats it as a checklist you return to, not a one-time sheet, and it asks each time whether demolition is clear to start or restart.

The demolition safety checklist, section by section

SectionWhat gets checked
Project detailsProject, site, start date, permit numbers
Pre-demo survey and permitsEngineering survey received and approved, permit posted, disconnect certificates uploaded, water, gas, electric and sewer cutoffs confirmed
Hazardous material abatementAsbestos survey done before demolition, asbestos notification submitted on time, lead and PCB removal plan, waste manifests, certified abatement contractor
Safety program and briefingWritten demolition safety plan, crew briefing, roles assigned (rigger, signal person, blaster)
Fire and public protectionFire safety plan approved, hot work permits, fire watch, perimeter fencing and signs, covered walkways
Structural controlsShoring and bracing to the engineer's design, marked drop zones, guarded floor openings and edges, a drop sequencing log
Debris handling and recyclingDust control, debris and recycled volumes in cubic yards, recycling rate, waste receipts
Deficiency logCrew briefed, clear to start or restart, each finding with action, owner, due date and status
Sign-offSuperintendent or competent person, safety manager, environmental compliance officer, and each worker's acknowledgment

Each section has a Yes/No and a note for every line, plus photos where they matter.

Demolition JHA requirements (OSHA and standards)

The form lists what it draws on: OSHA 29 CFR 1926 Subpart T for demolition, including the engineering survey in 1926.850(a), and 1926.501 for guarding open edges and floor openings. It also cites ANSI/ASSP A10.6 for demolition safety programs, NFPA 241 for fire safety during demolition, the EPA asbestos NESHAP for surveys and notification, EPA RCRA guidance for hazardous debris, and IBC Chapter 33 for safeguards during construction. Your state, city and permit conditions may add more, and rules get updated, so check the current versions before each job.

Run it on site or download it free

In Workyard the demolition JHA runs as a digital JHA on the superintendent's phone at clock-in or on the job, with photos, crew signatures on screen, any No flagged to a named person, and every update filed to the job for PDF or CSV export. Clear the site after with the post-demolition cleanup checklist, or browse more JSAs and JHAs. You can also download it free as a PDF, Word or Excel file, no sign-up needed.