A foundation inspection checklist is the form a superintendent, foundation contractor or inspector fills in before concrete goes into footings, walls or a slab: excavation, forms, rebar, anchors, waterproofing, drainage and slab prep, each marked Pass or Correction Needed, ending in a decision to pour or hold. Home builders, concrete contractors and general contractors use it on houses and commercial buildings alike.

What's on the foundation inspection checklist

The checklist works from the dirt up. Each section has its own photos, and every line gets a condition and a note.

SectionWhat you check
Project detailsPermit or job number, survey reference or gridline, soils report ID, weather
FootingsExcavation width, bottom at bearing and frost depth, base compacted and clean, forms braced, plumb and square, keyways and dowels placed
Reinforcement and hardwareBar size and spacing, concrete cover, laps and hooks, chairs stable and bars tied, anchor bolts and hold-downs set, grounding electrode in place, sleeves and embeds located
Waterproofing and drainageMembrane continuous, drain tile at the footing with fall, gravel envelope, filter fabric over the gravel, cleanout risers capped
Slab-on-grade prepVapor barrier sealed at laps, rigid insulation, plumbing and electrical stub-ups capped and braced, mesh or rebar on chairs, dowels at control joints
Final reviewApproved to pour, or pour on hold
Sign-offInspector or building official, plus the superintendent and a third-party engineer where required

Some lines carry typical values, such as 3 inches of cover against earth and 2 inches against forms, or a 10-mil vapor barrier. Your drawings, specs and soils report come first. The form lists the codes its sections are built on: IRC Section R403 for footings, IBC Chapter 18 for soils and foundations, and ACI 318 for cover and reinforcement details. Check which editions your jurisdiction has adopted.

Pass, correction needed and pour on hold

Every item is either Pass or Correction Needed, and the rule is simple: anything marked Correction Needed gets fixed and checked again before the pour, unless the form says otherwise. The final review has two answers. If every item passes, the foundation is approved to pour. If anything is still open, the pour is on hold.

That hold is the point of the form. Once concrete is placed, a bar that's short on cover or an anchor bolt in the wrong spot means a core drill, an epoxy anchor or a tear-out, and a missing stub-up means cutting the slab. Holding a truck costs an hour; fixing a slab costs days.

How to run the inspection before the pour

  1. Do your own check before the building official or engineer comes out. Their visit should find nothing you didn't already fix.
  2. Pull the permit, survey reference and soils report ID onto the form, so the inspection ties to the right drawings.
  3. Walk the footings first, then rebar and hardware, then waterproofing and drainage, then slab prep if there is one.
  4. Mark each line and take photos, especially of anything that will be buried: rebar, drain tile, stub-ups and the vapor barrier.
  5. Fix the corrections, re-check them, and update the line before you change the decision.
  6. Choose approved to pour or on hold, and collect the signatures your job needs.

Once the foundation passes, the concrete pre-pour checklist covers the pour itself: forms, embeds and the mix. For a closer look at the steel, use the rebar inspection checklist.

Get the checklist free or run it on a phone

Download the foundation inspection checklist free as a PDF, Word or Excel file, no sign-up needed. Or run it in Workyard's construction inspection app: the superintendent fills it in on a phone at the footings, photographs everything before it's buried, gets signatures on screen, corrections go to a named person, and every inspection is filed to the job in the office, ready to export as a PDF.